WWW - TIP Amendments

September 18, 2019

Washington County Amendments

Project #: PID 105024 (WAS-Marietta-Signals)
Project Description: Construction of traffic signals and fiber optic interconnecting system.
WAS-7-21.88- 25.01, WAS-60-0.28-1.44, and WAS-26-0.00-0.34.
Schedule: Preliminary Engineering (Detail Design) - FY 2020 Construction - FY 2021 (Phase 1)
Amendment: Detail Design added to the project in FY 2020- $38,992.
Revised construction cost to reflect Phase 1 construction in FY 2021 - $728,061.40

May 15, 2019

Washington County Amendments

Project #: PID 91758 (WAS-SR 7-17.60)
Project Description: Corridor rehabilitation with access control and drainage correction on SR 7- 17.60-20.57. Includes asphalt resurfacing, guardrail, pavement marking and minor turn radius improvements on WAS-TR 720-0.00-1.15.
Schedule: Construction - Fiscal Year 2020
Amendment: The construction cost is being increased from $3,445,000 to $4,280,000

Wood County Amendments

Project #: MOVTA (Section 5339)
Project Description: Purchase two replacement buses.
Total Project Cost: $230,000
Schedule: Fiscal Year 2020

March 20, 2019

Washington County Amendments

Project #: PID 91758 (WAS-SR 7-17.60)
Project Description: Corridor rehabilitation with access control and drainage correction on SR 7- 17.60-20.57. Includes asphalt resurfacing, guardrail, pavement marking and minor turn radius improvements on WAS-TR 720-0.00-1.14.
Schedule: Construction - Fiscal Year 2020
Amendment: The project description is being revised to include improvements to TR 720. Additionally, the project includes MPO funding requiring the project to be moved from the Statewide Line Item list to the project list subject to amendments.
Total Project Cost: Cost increased from $3,027,000 to $3,445,000.

Wood County Amendments

Project #: U354-002-22.11 07 (NHPP-0002(595)D)
Project Description: WV 2: Reconstruct to 5 lanes from 0.16 miles north of CR 3/8 to 0.34 miles north of WV 31. (GO BOND).
Schedule: Right-of-Way scheduled in FY 2019.
Amendment: Right -of-Way cost being revised from $2,000,000 to 25,500,000.

December 19, 2018

Washington County Amendments

Project #: PID 99479 (WAS-SR 676-24.00)
Project Description: Landslide repair on WAS-SR 676-24.00. Work includes upgrading storm water drainage system, sidewalks, curb and gutter, as well as upgrading guardrail and resurfacing.
Schedule: Construction - Fiscal Year 2020
Amendment: Right-of-Way phase added to the project in Fiscal Year 2019. The phase cost is $5,000 utilizing 100% local funding.

Project #: PID 105013 (WAS-WWW-Planning)
Project Description: WWW (MPO) regional transportation planning supplemental funding. Funding to be applied to the FY 20 Work Program.
Amendment: Project Deleted

Project #: PID 105014 (WAS-WWW-Planning)
Project Description: WWW (MPO) regional transportation planning supplemental funding. Funding to be applied to the FY 21 Work Program.
Amendment: Project Deleted

September 19, 2018

Wood County Amendments

Project #: MOVTA (Section 5339)
Project Description: Purchase two 30ft. or less replacement buses.
Total Project Cost: $190,000 ($152,000 federal and $38,000 local)
Schedule: Fiscal Year 2020

Project #: MOVTA (Section 5339)
Project Description: Purchase two 30ft. or less replacement buses.
Total Project Cost: $190,000 ($152,000 federal and $38,000 local)
Schedule: Fiscal Year 2021

Project #: MOVTA (Section 5310)
Project Description: Mobility Management Project. The project will expand the regular fixed routes serviced outside the normal ¾ miles boundaries targeting seniors, disabled, and low income individuals. The grant will help in developing a call center for all transit needs and coordinate with other providers through the call center.
Total Project Cost: $100,000 ($80,000 federal and $20,000 local)
Schedule: Fiscal Year 2019

July 13, 2018

Wood County Amendments

Project #: MOVTA (Section 5339)
Project Description: Purchase five replacement buses. Includes moving previously scheduled bus replacements from Fiscal Year 2020 (2 buses) and Fiscal Year 2021 (2 buses), as well as adding one bus not previously programmed on the TIP.
Total Project Cost: $619,200
Schedule: Fiscal Year 2019

Project #: MOVTA (Section 5339)
Project Description: Purchase one supervisors support vehicle.
Total Project Cost: $43,750
Schedule: Fiscal Year 2019

March 21, 2018

Wood County Amendments

Project #: U354-002-22.11 07 (NHPP-0002(595)D)
Project Description: WV 2: Reconstruct to 5 lanes from 0.16 miles north of CR 3/8 to 0.34 miles north of WV 31.
Total Project Cost: $2,000,000
Schedule: Right-of-Way scheduled in FY 2019

December 20, 2017

Wood County Amendments

Project #: MOVTA (Section 5339)
Project Description: Upgrade existing security cameras on buses.
Total Project Cost: $75,000 ($60,000-Federal, $15,000-Local)
Schedule: Fiscal Year 2019

Project #: MOVTA (Section 5339)
Project Description: Purchase and install maintenance bus lift for the bus garage.
Total Project Cost: $75,000 ($60,000-Federal, $15,000-Local)
Schedule: Fiscal Year 2019

September 13, 2017

Wood County Amendments

Project #: S354-77-0.00 00 (NFA-2217(015)D)
Project Description: I-77: Replace inlets/grates in District 3. (GARVEE)
Total Project Cost: $290,000
Schedule: Construction - Fiscal Year 2018

Project #: S354-77-158.69 00 (NFA-2217(012)D)
Project Description: 1-77: Culvert replacement project. Pond Creek Expressway Drainage. (GARVEE)
Total Project Cost: $150,000
Schedule: Construction - Fiscal Year 2018

Project #: S354-14-15.20 00 NHPP-0014(170)D
Project Description: Grand Central Avenue: Replace curb ramps for ADA compliance from Emerson Avenue in Parkersburg to 34th Street in Vienna.
Total Project Cost: $217,000
Schedule: Construction - Fiscal Year 2018

Project #: S354-68-17.90 00 (STP-0068(176)D)
Project Description: Replace curb ramps for ADA compliance on WV 68 in Parkersburg. Locations include Murdoch Ave. from 8th Street to Emerson Ave., 4th Street from Ann St. to Green St., and Ann Street from the bridge ramp to 5th Street. Project also includes a section in Williamstown on Highland Ave, from 3rd Street to 8th Street.
Total Project Cost: $207,000
Schedule: Construction- Fiscal Year 2018

Project #: S354-14-11.08 00 (STP-0014(169)D)
Project Description: South Parkersburg - Construct ADA compliant curb ramps on WV 14 from Gihon Rd./Rayon Dr. intersection to WV 95, and on WV 95 from Division St. to Elder St.
Total Project Cost: $155,000
Schedule: Construction - Fiscal Year 2018

Project #: U354-PAR/KE-13.00 (TEA-2014(107)D)
Project Description: Parkersburg - Construct Ohio River Trail from Point Park to Memorial Bridge. Includes construction of a pedestrian bridge over Pond Run.
Total Project Cost: $500,000
Schedule: Construction - Fiscal Year 2018

Project #: U354-WIL/LI-5.02 (TEA-2012(646)D)
Project Description: Williamstown Sidewalk Improvement project (Henderson Ave. and 8th Street).
Total Project Cost: $212,500
Schedule: Project being included in Fiscal Year 2018 for federal reimbursement.